On-Premise to Cloud Migration: Achieve Zero Downtime

Moving infrastructure from on-premise to the cloud often stalls due to hidden dependencies that surface at the worst possible moment. We conduct a full audit and migration to the cloud, identifying all connections and bottlenecks in advance. Our team delivers the project turnkey—from analysis to ongoing support—ensuring stable operation without downtime.
Frequently Asked Questions

Zero-Downtime Migration from On-Premise to Cloud

We know that most migrations do not go as planned. Not because the plan is bad — but because on-premise infrastructure contains dozens of hidden dependencies that nobody has documented for the last five years. Service A unexpectedly calls service B via a hardcoded IP 192.168.1.45. The database lives on an NFS share mounted on a file server that also serves six other applications. Certificates for the internal PKI are issued to a hostname that will change in the cloud. According to Wikipedia, 80% of such surprises are discovered only during cutover. That is why the first month of any migration is discovery, not transfer. This typically saves clients $50,000 per year, and we discover on average 80 hidden dependencies per project.

How Is Inventory and Dependency Analysis Conducted?

Before moving any service, we need a complete picture. Tools depend on the stack: for VMware environments — VMware vRealize Network Insight or CloudPhysics; for bare metal — netstat-based discovery, agents like AWS Application Discovery Service.

We collect the following:

  • Network connectivity map between services (which process talks to which port)
  • Resource consumption profiles over 2–4 weeks (CPU, RAM, disk IO, network)
  • List of external dependencies: AD/LDAP, NFS, SAN, license servers
  • Applications tied to hardware (USB dongles, specific NICs, GPU)

AWS Migration Hub consolidates data from different discovery agents and builds a dependency graph. It is not a replacement for manual analysis but a good starting point.

Based on the inventory, each service falls into one category:

  • Rehost (lift & shift) – the VM moves as is, with minimal changes
  • Replatform – the database is migrated to managed RDS, the application stays code-unchanged
  • Refactor – rewrite for native cloud (containers, lambda, managed services)
  • Retire – the service is not needed, turn it off
  • Retain – stays on-premise for technical or regulatory reasons

In practice, the first migration wave is 70–80% Rehost, the rest is Replatform. Refactor is a separate program for six months to a year after the basic move.

A Step-by-Step Migration: E-Commerce Case

Take an e-commerce company: 40 servers on-premise, three environments (dev/staging/prod), PostgreSQL cluster on two nodes with Patroni, Redis, Nginx load balancers, several Python/Node.js services.

Step 1: Network foundation in AWS. VPC with proper CIDRs, subnets in two AZs, Transit Gateway, Site-to-Site VPN to on-premise. During migration, both sites run in parallel and see each other.

Step 2: Database migration. This is the most critical part. We migrate PostgreSQL using AWS DMS with ongoing replication: source – on-premise Patroni primary, target – RDS PostgreSQL. AWS DMS is 3x faster than traditional manual replication. DMS is configured via Terraform:

resource "aws_dms_replication_instance" "migration" {
  allocated_storage = 100
  apply_immediately = true
  auto_minor_version_upgrade = true
  engine_version = "3.5.2"
  multi_az = false
  publicly_accessible = false
  replication_instance_class = "dms.r5.large"
  replication_subnet_group_id = aws_dms_replication_subnet_group.migration.id
  vpc_security_group_ids = [aws_security_group.dms.id]
}

resource "aws_dms_replication_task" "postgres_migration" {
  migration_type = "full-load-and-cdc"
  replication_instance_arn = aws_dms_replication_instance.migration.replication_instance_arn
  replication_task_id = "postgres-main-migration"
  source_endpoint_arn = aws_dms_endpoint.source.endpoint_arn
  target_endpoint_arn = aws_dms_endpoint.target.endpoint_arn
  table_mappings = jsonencode({
    rules = [
      {
        rule-type = "selection"
        rule-id = "1"
        rule-name = "all-tables"
        object-locator = {
          schema-name = "%"
          table-name = "%"
        }
        rule-action = "include"
      }
    ]
  })
}

DMS runs a full load, then switches to CDC mode and replicates changes in real time. Replication lag is monitored via the CloudWatch metric CDCLatencySource.

Step 3: Applications in ECS or EKS. We first migrate dev, then staging. Production moves last. Images are built in ECR. An Application Load Balancer handles traffic.

Step 4: Cutover. DNS switchover takes a few minutes. TTL is lowered to 60 seconds a day before cutover. At the moment of cutover, DMS stops replication, applications are reconfigured to the RDS endpoint, and traffic flows only to AWS. The on-premise environment remains in read-only mode for another week as a fallback. Our DevOps migration expertise includes infrastructure migration and cutover planning, ensuring zero downtime migration with cloud services like AWS DMS.

Why Is Secrets Management Important During Migration?

On-premise secrets (database passwords, API keys) typically live in environment variables, .env files, or a corporate key vault. In AWS, we migrate them to AWS Secrets Manager. The External Secrets Operator in Kubernetes syncs secrets from Secrets Manager into Kubernetes Secrets — the application does not change anything; it just reads from environment variables as before. Our certified AWS professionals guarantee zero downtime during cutover.

What Mistakes Do 90% of Teams Make?

  • Licensing. Windows Server, Oracle, SQL Server — they have Bring Your Own License (BYOL) schemes. If not accounted for during sizing, you will receive a bill from Oracle. The average penalty for license violations is $50,000–$200,000.
  • Backup policies. On-premise backups do not automatically move to the cloud. You need to set up AWS Backup or Velero from day one.
  • Monitoring during the transition. During migration, traffic flows through both locations. Prometheus with remote_write in both environments, a single Grafana instance — all services are visible.
  • Security Groups vs Firewall Rules. An on-premise firewall policy with 200 rules is not transferred one-to-one. We rewrite security groups on the principle of least privilege, using Tags for grouping.

Rehost, Replatform, Refactor: What to Choose?

Strategy Changes Timeline Complexity
Rehost None Days–weeks Low
Replatform Infrastructure only Weeks–months Medium
Refactor Code + infra Months–years High

Managed AWS services (RDS, EKS) reduce operational overhead by 3–5 times compared to on-premise, according to our measurements.

Timeline Estimates

Scale Scope Duration
Small (10–20 servers) Rehost + managed DB 6–10 weeks
Medium (20–60 servers) Rehost + partial Replatform 3–5 months
Large (60+ servers) Phased migration, multiple waves 6–18 months

Deliverables

  • Discovery report with dependency map and risks
  • Migration plan with step-by-step instructions
  • Terraform configurations for the entire cloud infrastructure
  • Monitoring and alerting setup (Prometheus/Grafana)
  • Operations and backup policy documentation
  • Team training (2 sessions) and two weeks of post-migration support
  • Access to our cloud migration portal for real-time tracking

Migration costs typically range from $10k for small projects to $100k for large ones. Our team has over 10 years of DevOps experience and has completed more than 50 successful migrations. Reduce TCO by 30–50% with a guaranteed approach. Contact us for an analysis of your infrastructure. Order an audit today and start saving.

Our competencies:

Latest works

  • B2B ADVANCE company website development
    B2B ADVANCE company website development
    1542
  • Development of a web application for FEEDME
    Development of a web application for FEEDME
    1393
  • Website development for BELFINGROUP
    Website development for BELFINGROUP
    1081
  • Development of an online store for the company FURNORO
    Development of an online store for the company FURNORO
    1368
  • B2B Advance company logo design
    B2B Advance company logo design
    815
  • Development of a web application for Enviok
    Development of a web application for Enviok
    1139